What is the maximum size of a construction project before a sediment/retention pond becomes necessary?

Prepare for the Virginia Highway Heavy (H/H) Exam with our comprehensive quiz. Study with flashcards, multiple choice questions, and detailed explanations for each query. Ace your exam!

The requirement for a sediment or retention pond is primarily governed by regulations aimed at controlling erosion and managing stormwater runoff during construction projects. For many jurisdictions, including Virginia, a project that disturbs 10 acres or more is typically considered the threshold at which a sediment control plan, including the installation of a sediment/retention pond, is required.

This regulation is designed to address the significant environmental impacts associated with larger disturbed areas, which are more likely to contribute to sedimentation and runoff issues. Proper management of stormwater and sediment is crucial to minimize the impacts on local waterways and ecosystems. Thus, projects at or exceeding the size of 10 acres necessitate these measures to support effective erosion and sediment control practices.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy